Week 1- 9/11/15
.Creating draft ideas
.Experimenting with different magazine conventions
.Create rough designs for my products
Week 2- (16/11/15)
.Completed photoshoot for all of my products
.Started designing front cover on photoshop
Week 3- (23/11/15)
.Creating front cover using Photoshop
Week 4- (30/11/150
.Creating front cover in photoshop
Week 5-(7/12/15)
.Completed front cover
. Started designing the contents page using photoshop
Week 6-(14/12/15)
.Creating contents page on Photoshop
Week 7- (11/1/16)
.Completed contents page
.Started designing double page spread in Indesign
Week 8- (18/1/16)
Creating double page spread on Indesign
Week 9-(25/1/16)
.Completed double page spread
.Going over final products to add any final changes
Week 10- (1/2/16)
.Going over final products and adding any changes
Week ll- (8/2/16)
.Final products completed